With the date of 31th January 2016 the following works have been terminated:

-          the renewal of the Lake Bükki

-          the structural works of  the prohibited relief, related to the 3rd and 4th lakes of Kűvölgy and Lake Baláta, as well as the entrapment of the water streams.

 

The implementation passed off in order. The technical handover-takeover is going to take place on 16th February 2016.

 

Lake Bükk                                                                           Lake Kűvölgy

At the end of the implementation the completed works were being introduced to the forester and hunter collegaues.

 

 

The by-pass was constructed to regulate runoff from Lake Baláta.

On the 8 January 2016 the first bottom step was constructed. This aims to slow the streamlets, in order to raise the water level, which will provide ground water to the trees in the surrounding forests.

  

On 15 December 2015 the I. phase of the construction works was completed: dredging of Kűvölgy #2, reinforcement of the barrage and road reconstruction were carried out. Technical delivery/acceptance procedure was completed, the construction was finished successfully.

                            

 

Works related to the II. phase of the implementation are advancing well. The barrage of Lake Bükki was reinforced and stilted, the central regulation structure is under construction.

At the barrages of Kűvölgy #3 and #4 wave protection is already under construction after completion of the embankments and regulation structures.

 

Reinforcement of the embankment at Lake Bükki                                      Installation of the central regulating structure at Lake Bükki

 Barrage of Lake Bükki

  

Barrage at Kűvölgy #4 being built                                                               Construction of the wave protection at Kűvölgy #4

 

Barrage at Kűvölgy #3 under construction                                                   Barrage of Kűvölgy #3